
2017年6月上第46卷第11期
DOI:10. 7672/sgjs2017110021
施工技术
CONSTRUCTION TECHNOLOGY
1-130m系杆拱桥斜拉扣挂系统施工技术
李平
(中铁六局集团太原铁路建设有限公司,山西太原030013)
[摘要]太兴铁路柳林河一号1-130m钢箱式系杆拱桥,位于太原汾河二库内,上跨柳林河,两侧地形陡峻,起伏较大,呈U形,地面标高相对高差约95m,两端均与隧道相连,其中小里程侧0号台距隧道口20m,大里程侧1号台距隧道口7.01m。采用缆索起重机斜拉扣挂法整体拼装的施工方法,同时根据现场实际情况,自行设计缆索起重机缆扣系统,满足现场实际施工需要。
【关键词】桥梁工程;系杆拱桥;缆索起重机;斜拉扣挂;拼装;施工技术
[中图分类号】U448.22
【文献标识码]A
[文章编号]1002-8498(2017)11-0021-04
ConstructionTechnologyofInclined Cable-stayedBuckleSystemfor
TiedArchBridgewith1-130m
LIPing
(Taiyuan Railuay Gonstruction Go., Lid.of China Railuay Sixth Group Co., Lid.,
Taiyuan,Shanxi030013,China)
Abstract:The No. 1 1-13Om steel box tied arch bridge on Taixing Railway Willow River locates in Taiyuan Fenhe Two Reservoir, across Willow River, on both sides of steep terrain, undulating, which assumes U type, relative height of ground elevation is about 95m, both ends are connected with tunnels, the small side No. O distance from tunnel mileage is 20m, high mileage side No. 1 distance from tunnel is 7. O1m. The whole construction method of cable-stayed cable stayed buckle is adopted. According to the actual situation of the site, the inclined cable-stayed buckle system is designed, which can meet the actual needs of the construction site.
Key words : bridges ; tied arch bridges ; cable crane ; inclined cable-stayed buckle ; assembly ; constructior
1工程概况
山西省太兴铁路柳林河一号大桥为钢箱式系杆拱桥拼装结构,位于太兴铁路太静段土堂一柳林河间,中心里程为DK22+814.5,全长138.969m(见图1)。桥址位于汾河二库内,上跨柳林河,两侧地形陡峻,起伏较大,呈U形,地面标高相对高差约
95m。两端分别与新柏崖头隧道和新柳林河隧道相连,其中小里程侧0号桥台与新柏崖头隧道出口距离为20m,大里程侧1号桥台与新柳林河隧道明洞入口距离为7.01m。
本钢桥为1-130m下承式单线铁路简支系杆拱
桥结构,由拱肋、系杆、吊杆、横撑、横架、桥面板组成,其中拱肋、系梁、横撑为箱体,吊杆为H形,横梁为T形,桥面板为正交异性板。
【作者简介]李平,高级工程师,E-mail:gjm0711@126.com【收稿日期]月厉数据;【修订日期】2017-03-26
图11-130m系杆拱桥效果
Fig.1 Effect of the tied arch bridge with 1-130m 2桥梁施工顺序
21
在加工厂完成所有钢结构构件的加工、制作及预拼装,现场按照先拱后梁的顺序进行安装:①第1 步安装拱肋,首先进行80t缆索起重机系统、扣错系统、吊装场的施工,然后采用支架法安装拱脚GX 节段以及相应的桥面板,随后按顺序采用缆索起重机吊装,斜拉扣挂法安装拱肋节段和横撑,最后完成合龙段安装,完成拱肋部分施工;②第2步两岸