
14
D0I;10.7672/sgjs2014200014
施工技术
CONSTRUCTION TECHNOLOGY
2014年10月下第43卷第20期
天津嘉里中心酒店大跨度钢桁架安装滑移施工技术
高元仕,范围,王忠,路兰,于有为,黄勇
(中建一局集团建设发展有限公司,北京100102)
【摘要】天津嘉里中心酒店大宴会厅屋顶布置6榻大跨度钢桁架。鉴于工程特点和施工难点,本工程钢桁架采用滑移安装施工技术。重点介绍了履带式起重机行走路线,滑移轨道铺设,桁架吊装、滑移、就位、焊接、卸载等施工工艺。指出桁架滑移过程中还需对桁架两端的混凝土梁进行实时监测,监测混凝土桑的下挠值、检查混凝土梁表面是否有裂纹出现等。
【关键词】钢结构;桁架;吊装;滑移;卸载;施工技术
【中图分类号】TU758
【文献标识码]】A
【文章编号】1002-8498(2014)20-0014-04
Large-span SteelTrussInstallation SlidingConstruction
inTianjinJialiCenterHotel
GaoYuanshi,Fan Wei,Wang Zhong,Lu Lan,YuYouwei,HuangYong(China Construction First Group Construction & Development Co.,Lad., Bejing 100102,China)
Abstract: Six large-span steel trusses set in Tianjin Jiali Center Hotel roof. Combining with the engineering characteristics and construction difficulties, the sliding installation technology was used. The crawler crane rout, sliding track layout, and hoisting, sliding, location, welding, unloading of trusses were introduced in detail. It is pointed out that during sliding of the trusses, the real time monitoring for concrete beam should be done, which monitor the deflection of concrete beam and check the surface cracks, and so on.
Key words:steel structures; trusses; hoists; sliding; unloading; construction
1工程概况
天津嘉里中心酒店大宴会厅南北方向跨度 59.5m,东西方向跨度34m,顶部布置6福桁架,两侧支座分别为轴和轴900mm×1000mm钢筋混凝土大梁。桁架材质为Q345GJC及Q345C。 GHJ2桁架上、下弦为口形截面,主要形式有 600mm×600mm×50mm×60mm等;腹杆为H形截面,主要形式有600mm×600mm×60mm×60mm 等。GHJ3桁架上弦、下弦、腹杆皆为H形截面,主要形式有600mm×500mm×50mm×50mm等。如
图1所示。 2施工部署
2.1施工方案确定
1)每榻桁架分3段,每段质量均在19t以上,最重一段达33t。根据分析现场已有的9号塔式起重机覆盖范围内的起吊荷载,无法满足桁架的吊装
【作者简介】高元仕,工程师,E-mail:gyuanshi@163.com
[收稿日期】2014-03-28 万方数据
????
要求。
梧架区城
2345689
图1桁架平面布置
Fig.1Plan arrangementof trusses
2)若履带式起重机进入室内对?~?轴桁架进行吊装,履带式起重机的行走区域将大大加大,履带式起重机进、出场费用及加固区域措施费用也会大大增加;同时结构必须考虑预留,工序复杂,拖延工程进度。
3)桁架安装高差大,若全部采用满堂脚手架进行高空拼装费用高,且施工时间长,对工程进度有