2(【道桥面系施工方法,包括桥面系施工流程,施工组织及关键施工控制措施,并总结施工中需要注意的问题及解决方法。工程施工质量满足现行规范及设计要求。
[关键词】桥梁工程:铁路工程:桥面系:施工技术
【中图分类号】TU576;U455.4
【文献标识码]A
【文章编号】1002-8498(201212-0031-03
ConstructionTechnologyofBallastTrackBridgeDeck
SysteminXiamen-Shenzhen Railway Cheng Zhihua, Ma Chengqiang, Wu Jian
(No.8 Detachment, Ne.2 Hydropower Foree of Armed Police, Xiamen, Fujiaa361009, Chine)
Abstract:Combined with Luohe bridge in XSGZQ-7 biding of front-station project in Xiamen-Shenzhen railway, the construction technology of ballast track bridge deck system in high-speed railway is discussed, including construction process, construction organization and key points of construction control methods. The key points and solving methods of construction are summarized. The eonstruetion quality meets the requirements of code and design.
Key words:bridges; railway engineering; bridge deck system; construction
1工程概况
厦深铁路广东段站前工程XSCZQ-7标段螺河特大桥起里程DK320+582.890—DK333+ 633.268,全长13050.38m,桥面布置采用有轨道整孔双线箱梁形式。桥面系线路左右两侧设计为"挡雄墙+竖墙B+竖墙A+遮板+栏杆"结构。桥梁两侧为钢筋混凝土组合栏杆,跨越密集居民区设置声屏障。挡咋墙及竖墙现场浇筑,采用C40高性能混凝土:电缆槽盖板、桥染遮板、栏杆采用小型构件预制厂集中预制:桥染表面(含电缆槽)设防水层,防水层采用改性沥青防水卷材和无需卷材的案氨醋防水涂料型防水层施工工艺;防水保护层采用现浇60mm厚C40细石聚丙烯纤维网或聚丙烯睛纤维混凝土;每跨连接处设置伸缩缝,伸缩装置采用厂购成品伸缩缝进行现场安装。厦深铁路螺河特
大桥桥面系结构如图1所示。【收精日期】2012-03-17
【基金项日]武警水电第二总队2012—2014年度科研规刘项目队排长,助理工翟师,广东省陆丰市东海经济开发区东海大道
516500,电话;18688079727,E-msil,516665935@ qq. com 万方数据
声解障指啡墙
中心线
经略中心司钱路分界快
工线
2.026 2.0%
图1桥面系结构示意
Flg.1
31
保护层栏杆防水层
拉能裤
Structure of bridge deck system
2主要施工方法及工艺 2.1桥面系施工流程
桥面系包括:挡咋墙、竖墙B、竖墙A、接触网支柱基础施工,遮板、栏杆(声屏障)预制及安装,桥面防水层铺设,伸缩缝安装,桥面保护层施工,电缆槽盖板的预制和安装等。
桥面系施工工艺流程如图2所示。 2.2桥面系施工工艺
2.2.1挡碑墙、竖墙施工 2.2.1.1施工步骤
线型控制和高程控制→+预埋筋除锈→基层凿毛→+钢筋绑扎→模板安装→混整土浇筑→+养护→