某电厂旋喷桩施工对冷却水塔基础的挤土分析
潘巨思,姚伟锋
(中国能源建设集团浙江火电建设有限公司,浙江杭州310016)
[摘要]某工程中冷却水塔基础与循环水管高压旋喷桩需同时施工,而高压旋喷桩桩中心离冷却水塔池壁间距只有3.1m。在高压旋喷桩施工过程中由于土体挤压冷却水塔池壁和基础,引起冷却水塔底板垫层起拱,已施工完成
【关键词]桩:高压旋喷桩:挤土;隔离带;施工技术
[中图分类号]TU744
【文献标识码]A
[文章编号】1002-8498(2016)07-0059-03
Analysis ofSoilCompactionwithJetGroutingPileConstructionto
Power Plant Cooling Tower Foundation
Pan Juzhong,Yao Weifeng
( Zhejiang Thermal Power Construction Co. , Lid. of China Energy Engineering Group,
Hangzhou,Zhejiang310016,China)
Abstract : Cooling tower foundation must construct at the same time with high pressure jet grouting pile of circulating water pipe. But the center of high pressure jet grouting pile wall spacing from the cooling tower is only 3.1m.In the high pressure jet grouting pile construction process,because of the soil extrusion to foundation and the wall of cooling towers,the floor mat bagging, and completed construction of the wall top and side portions are produced through the cracks.The treatment measures were analyzed and introduced.
Key words : piles; high pressure jet grouting piles; soil compaction; isolation strip; construction
1工程概况
某电厂施工区域为海涂围垦区域,回填塘渣层厚近4m,水位常年偏高,-4.000m以下多属淤泥质七,本工程循环水管地基处理设计采用800高压旋喷桩。为了保证按时送电,冷却水塔基础与循环水管安装施工必须同步进行,也就是冷却水塔基础与高压旋喷桩需同时施工,而循环水管的高压旋喷桩桩中心离冷却水塔池壁间距只有3.1m(见图1)。在高压旋喷桩实际施工过程中由于打桩产生的土体挤压冷却水塔池壁和基础,引起冷却水塔底板垫层起拱,已施工部分池壁顶面与侧面均产生了贯穿性裂缝。
2主要影响因素分析
高压旋喷桩施工对冷却水塔基础造成了影响因高压旋喷桩不与冷却水塔基础直接接触,所以高【作者简介]潘巨忠,高级工程师,国家一级注册建造师,E-mail: 664920789@ qq. co
[收稿日期]2015-04-09;[修订日期】2015-09-20
59
压旋喷桩施工产生的挤土直接作用于冷却水塔基础引起施工中的薄弱环节(冷却水塔基础垫层部分和混凝土养护强度不足部分)造成起拱和开裂破坏,因此需控制高压旋喷桩施工对冷却水塔基础的挤土破坏。本工程中,挤土破坏产生的原因主要为以下几方面,
1)冷却水塔混凝土强度不足
冷却水塔基础混凝土强度不足引起的挤土破坏主要体现在:高压旋喷桩施工时冷却水塔基础池壁浇筑完成仅2~3d,远未达到混凝土强度设计值;未浇筑基础底板部分的垫层强度较低,在高压旋喷桩施工时产生的挤土对其造成硬性破坏。
2)塘渣围垦
施工环境处在塘渣围垦段内,塘渣厚度达4m,集聚孔隙水,形成水压且地基回填时使用大石块较多。
3)施打高压旋喷桩速率过快
由于地下水位较高,打桩速率过快引起超孔隙