大截面框架柱清水混凝土施工模板支设技术
邓亮文,金五一,方涛
(中国建筑第二工程局有限公司核电建设分公司,广东深圳518034)
[摘要】以阳江核电厂CPA1000+机型框架柱清水混凝土施工为例,简要介绍大截面框架柱清水混凝土施工模板
支设的技术要点,能消除模板水平拼缝和埋件凹凸不平对清水混凝土效果的影响。【关键词]混凝土;模板;设计;安装;施工技术
[中图分类号]TU755.2*2
【文献标识码]A
[文章编号]1002-8498(2017)14-0025-03
FormworkSupportingTechnologyforConstructionofLarge
Section Column Frame Fair-faced Concrete
DENG Liangwen,JIN Wuyi,FANG Tao
( Nuclear Construction Branch, China Construction Second Engineering Bureau Co. , Lid. ,
Shenzhen, Guangdong 518034, China)
Abstract: Taking Yangjiang nuclear power plant with CPA1000 + type frame column fair-faced concrete construction as an example, the construction formwork of large section column frame fair-faced concrete supporting technology was introduced, which can eliminate the influence of the horizontal joint template
and embedded parts unsmooth to the effect of fair-faced concrete. Key words : concrete; formworks ; design; installation; construction
1工程概况
阳江核电广位于广东省阳江市东平镇充泊村,共建设6台100万千瓦级机组,常规岛汽轮发电机厂房平面尺寸为61m×100m,采用钢筋混凝土框排架结构形式,?,B,C每条轴线各有11根钢筋混凝土框架柱,@,B轴框架柱截面尺寸为1000mm×
2000mm,轴框架柱截面尺寸为1000mm× 1800mm,,轴跨距为47.5m,B,C轴跨距为 135m.汽轮发电机厂房屋架采用双坡梯形钢屋架 A排柱通过钢屋架与辅助间框架组成横向框排架结构(见图1),与纵向框架共同构成一个空间体系。 2施工说明
为节约工期,将框架梁柱一起施工,施工缝均
设置于梁面,部分柱需一次浇筑8m高混凝土,柱模板加固体系需经计算合格后方可使用,为保证模板受力性能满足要求,不能将框架柱混凝土一次浇筑至顶部,需同时施工5个以上框架柱,按1m/h控制混凝土浇筑速度循环浇筑,由于梁面钢筋密集,需提前安装PVC管下料口,确保混凝土自由下落高度
【作者简介】邓亮文,工程师,E-mail;275111898@qq-com【收稿日期]月厉数据
图1框架结构布置
Fig.1Frame structure arrangement
25
≤1.5m。为避免水平施工缝和模板拼缝影响整体清水混凝土施工效果,在水平施工缝处设置收口条,在模板拼缝处设置工字形明缝条。根据现场施工实际情况,选用2440mm×1220mm×18mm的竹木胶合模板、100mm×50mm木方、I14和I10、M16 高强丝杆、蝴蝶卡等作为模板支设材料。
3施工要点 3.1模板设计
柱模板全部采用18mm厚光面竹木胶合模板第1道背楞采用50mm×100mm木方,竖向布置,间距约200mm,柱箍短边方向采用2110,长边方向采用2114,间距≤600mm;柱箍两端必须使用M16高强螺栓,为了保证混凝土表面外观质量,柱中不设