汽提塔运行不稳定的原因和改进措施
赵省军·
(陕西北元化工集团有限公司,陕西榆林719319)
【关键词】PVC;汽提塔;残留VCM;塔板;堵塞;改进措施
Vol.43,No.12 Dec.,2015
【摘要】分析了汽提塔运行不稳定的原因,并进行了相应改进:严格控制汽提塔工艺参数,加强设备维护,提高操作人员技术水平。使汽提塔清洗周期延长至6个月,并提高了PVC的产量。
[中图分类号】TQ325.3
【文献标志码】B【文章编号】1009-7937(2015)12-001904
Causes of unstable operation of stripper and improvements
ZHAO Shengjun
(Shaanxi Beiyuan Chemical Industry Group Co. , Ltd. , Yulin 719319, China) Key words:PVC; stripper; residual VCM; tray plate; blockage; improvement measure
Abstract:Causes of unstable operation of stripper were analyzed. Improvement measurs were taken, including strict control of stripper process parameters, enhancement of equipment maintenance, improve-ment in technical level of operators. Thus the cleaning period of stripper was prolonged to 6 months, and the output of PVC was increased.
陕西北元化工集团有限公司(以下简称北元化工)100万VaPVC装置汽提塔是四川宜宾江源化工机械有限公司根据日本智索公司工艺配套制造的小孔溢流筛板塔。在使用初期,由于操作人员业务不熟练、工艺指标不清晰和控制水平差,汽提塔塔眼经常堵塞,浆料在塔内沸腾差,汽提结束后PVC树脂中VCM残留量超标,黑黄点较多,不得不经常停车清洗汽提塔。
经过分析汽提塔工艺参数,不断提高操作人员业务技能并规范工艺操作,现在汽提塔的整体运行情况较好,避免了汽提塔塔眼堵塞,汽提塔内浆料沸腾状况良好,树脂质量也得到了很大的改善,残留 VCM质量分数达到国家标准要求的5×10"杂质粒子数也得到了控制,减少了停车清洗汽提塔的次
数,为后续干燥工序的稳定运行莫定了基础。 1汽提塔简介
北元化工汽提塔的单塔生产能力为25万Va。
【收稿日期】20150304【修回日期】201512-11
该塔的结构简单独特,共有8层塔盘,塔盘间距 1.3~1.6m,通过塔节法兰固定。该塔设计有3个不同进料层(4层、6层、8层),可根据树脂牌号选择不同进料层。浆料在每层塔盘停留时间为3min,若从第8层塔盘进料,浆料在塔内停留时间大约为 24 min。
每层塔盘上均勾分布若干小孔,塔眼为孔径8 mm和1.2mm的阶梯孔。每层塔盘上还分布有 0.56m高的折流板、溢流堰和降液管,保证了浆料在塔盘上均匀、稳定流动。为防止汽提塔塔眼堵塞,每层塔盘的塔眼下一定距离处都设计了1组喷淋盘管,在开停车和正常运行时冲洗塔眼,每个喷淋盘管上一定距离前后左右也开有2mm的小孔,保证每次都能冲洗到塔眼。在运行时,由DCS自动控制喷淋装置对每层塔盘循环冲洗45s,有效防止塔眼堵塞。
汽提塔采用螺旋板式换热器和抽真空工艺。最