总茅250期 2016年第10别
河北冶金 HEBEI METALLURGY
昆玉钢铁2#、3#高炉复产开炉生产实践
飞,王广林
陈艳波,王庆鲲,蔚
(新疆昆玉钢铁有限公司,新摄奎电833200)
Total No.250 2016,Number10
摘要:2015年4月12日,4月19日昆玉钢铁公司2#、3#高炉分别在停炉165天、173天后开炉复产。本次开炉前期准备充分,开炉焦比选择准确,后续开风口、降焦比、布料角度调整紧漆合理,整个开炉过程
非常顺利,实现了安全、顺利开炉、快速达产的既定目标。关键词:高炉;开炉:实践
中图分类号:TF543
文献标识码:B
doi:10. 13630/j. cnki. 13 1172. 2016. 1010
文章编号:10065008(2016)10003806
PRACTICETOBLOW ON ANDRESTART
PRODUCTIONOFBLASTFURNACE2AND3INKUNYU
Chen Yanbo, Wang Qingkun, Yu Fei, Wang Guanglin(Xinjiang Kunyu Iron and Steel Co., Ltd.,Kuitun, Xinjiang,833200)
Abstract: After blowing off for 165 and 173 days, the blast furmace 2 and 3 of Kunyu blew on and restarted production in Apr. 12, and Apr. 19, of 2015. With full preparation before blowing on, accurate selection for blowing coke ratio, and compact and reasonable following steps: opening tuyere, reducing coke ratio and adjusting charge distributing angle, the all procedure was very smooth, the target of safe, blowing on and fast reaching the rated output is got.
Key Words: blast furnace; blow on; practice
0
引言
2015年4月12日22:26新疆昆玉钢铁公司炼
铁厂2#高炉送风点火,4月19日21:36炼铁厂3#高炉送风点火。炼铁厂2#、3#高炉分别在停炉165 天、173天后开炉复产。2#高炉送风6h后出第一次铁,消渣少许。第二次出铁放火渣1炉,出渣铁约7t。第三次出铁开始过撤渣器、冲水渣。当日18:50开始喷煤。4月14日13:42透平机投人使用,开炉25 h风口全开,4天后顺利达产,转人指标提升阶段。 3#高炉送风9h出第一次铁,滴渣少许。第二次出铁放火渣1炉,出渣铁约10t。第三次出铁开始过撤渣器、冲水渣。当日18:00捕开全部风口,恢复喷煤,3天后顺利达产,转人指标提升阶段。炼铁厂 2#、3#高炉开炉取得圆满成功。
此次开炉,由于前期准备工作充分,开炉焦比选收稿日期:201608-17
作者简介:陈艳波(1973-),男,工程师,1993年毕业于期南株洲冶金工业学校钢铁冶金专业,现在山东石横特钢集团新疆昆玉钢铁公
司从事炼铁生产研究工作,E-mail;5162370@qq.com 38
万方数据
择准确,后续开风口、降焦比、布料角度调整紧漆合理,整个开炉非常顺利。
1
开炉前的准备工作
安全教育培训 1.1
由于停炉期间员工放假,为了提高员工安全意识,尽快进人工作状态,开炉前对全部岗位员工进行培训。炼铁车间共组织培训25场,合计培训员工 365人次,先后组织了安全普考、上岗前技能考评,确保全部员工合格上岗。
制定完善各类方案、预索
1.2
为确保开炉顺利进行,炼铁厂先后制定了《炼铁厂开机、开炉设备恢复方案》、《高炉冷却水系统冲洗、试压方案》、《高炉本体喷涂方案》、《打压试漏方案》、《枕木填充方案》、《炼铁厂2#、3#高炉开炉方案》等方案、预案,并组织相关管理人员、岗位员工
进行学习,确保岗位员工对操作要点熟记于心。 1.3高炉本体喷涂造村
停炉后,发现2#、3#高炉5~10段冷却壁镶砖及前端所砌耐火砖衬基本全部脱落,10段、11段冷