10. 1 一般规定· 10.2 坡口制备 10.3 组对. 10.4预热. 10.5工艺要求 10.6焊后热处理. 10.7 焊接质量检验 11水压试验 11.1一般规定· 11.2试验前具备条件· 11.3试验 12锅炉附件 12.1一般规定 12.2汽包水位计· 12.3 安全阀· 12.4 压力表 12.5 温度测量仪表 12.6 吹灰器 12.7 门、孔类· 12.8 膨胀指示器· 12.9 特殊支吊架· 12.10 膨胀节· 13 烟风道及燃(物)料系统安装 13.1 般规定· 13.2 烟风道 13.3 烟风道附件· 13.4 给煤系统· 13.5 燃烧器系统· 13.6 除尘系统· 13.7 密封性试验 14脱硫、脱硝、灰渣系统安装 14. 1 般规定 14.2 烟气脱硫装置 14.3 烟气脱硝装置· 14.4 灰渣系统· 15筑炉、防腐、保温· 15.1 一般规定 15.2筑炉... 15.3防腐... 15.4 保温:
14 ·15 ·15 16 ·16 ·17 19
·20 20 ·20 21 ·21 -21 ·22 22 ·22 22 ·22 23 23 23 .23 .23 23 ·24 ·24 .25 25 25 27 27 ·27 ·28 ·28 ·28 ·28 28 .·29 ·33 ·33
II
SH/T3559—2017
Contents
V
Foreword.. Scope 2Normativereference
.
Terms and definition 4Basic provision
3
Foundation acceptance and lineation Material inspection* 6.1 General...... 6.2Structural steel frame inspection* 6.3 Heating surface material inspection 6.4 Affiliated pipe and fitting inspection' 6.5 Valve inspection.... 6.6Otheraccessoryinspection 7 Structural steel frame installation
5
6
7. 1 General.... 7.2 Beam and pillar installation..... 7.3Largeplatebeam* 7.4Suspension device.. 7.5Ladderandplatform
.6
8Air preheater installation*: 8.1 Tubular air preheater 8.2 Rotary air preheater 9Heating surface and affiliated pipline installation 9.1 General.. 9.2 Boiler drum and header* 9.3 Water wall.... 9.4 Superheater and desuperheater' 9.5 Economizer 9.6 Cyclone separator 9.7 Hood....
..9
0
10
·12 12 13 13 13 -13 13 14 14
9.8 Droppiplineand connectingpipline 9.9 Steam pipline and water supply pipeline 9.10Sampling and dosing pipline* 9.11 Blowdown pipeline and drain pipeline' 10 Welding and inspection' IV
14
SH/T3559—2017
-14 ·15 .·15 16 ·16 ·17 ·19 20 ·20 ..20 .·21 21 ?21 ...22 ·22 ·22 22 ...22 .·23 ..23 ..·23 .23 .·23 ·23 .·24 .**24 ·25 ·25 .25 27 ·27 .27 ..28 .-28 28 .28 .·28 29 ..33 ·33
10.1 General 10.2 Groove preparation 10.3 Fitting up' 10.4 Welding preheat.. 10.5 Process requirements' 10.6 Post weld heat treatment.. 10.7 Welding quality inspection...... 11 Hydrostatic test
11. 1 General... 11.2Preconditions for hydrostatic test 11.3 Hydrostatic test..
12Boileraccessories installation' 12.1 General.... 12.2 Drum water level gauge.. 12.3 Safety valve 12.4 Pressure gauge 12.5 Temperaturemeasurement instrument 12.6 Soot blower.. 12.7 Gate and hole.. 12.8 Expansion indicator 12.9 Special support. 12.10 Expansion joint 13 Smokeductandcombustion(medium)system installation..... 13.1 General.. 13.2 Smoke duct. 13.3 Accessories of smoke duct... 13.4 Coal supplying system.*. 13.5 Burner system· 13.6 Dustremoval system 13.7Leakagetestforsmokeductandcombustion(medium)system 14Desulphurization and denitration, ash system installation' 14.1 General.. 14.2Fluegasdesulphurizationdevice installation* 14.3Flue gas denitration device installation 14.4Ash and slag system installation* 15Refractory,thermal insulation andpainting' 15.1 General 15.2 Refractory 15.3 Insulation* 15.4 Painting'
V
SH/T3559—2017
.34
16Hightemperatureoven 16.1General 16.2Hightemperatureoven 17 Chemical cleaning of boiler*.
34
34 34
17.1 General... 17.2Precondition for chemical cleaning 17.3Chemical cleaning 18Starttrial operation' 18.1 General.... 18.2The boilerdebugging 18.3Steamblowingandpurging 18.4Steamleaktest and safetyvalve adjusting 18.5Adjustment and trial operation' 19Technical documents for hand over 19.1General.... 19.2Technical documentshandoverformatforboiler installation eneral AnnexA(Normative)Method statementforboilerpillar installationand alignment AnnexB(Normative)Ecommendgrooveformandsizeforweldingfittingup Explanation of wording in this specification' Add:Explanation of articles
34
34 34
35
35
·36 ·36 ·37
3
2
..38
..38
?58
.60 -64 65
VI
SH/T3559—2017
前言
根据中华人民共和国工业和信息化部《2012年第四批行业标准制修订计划》(工信厅科[2012]252 号)的要求,规范编制组经广泛调查研究,认真总结实践经验,参考有关国际标准和国外先进标准,并在广泛征求意见的基础上,制定本规范。
本规范共分19章和2个附录。 本规范的主要技术内容是:基本规定;基础验收及基础划线;材料检验;钢架安装;空气预热器
安装;受热面安装、附属管道安装;焊接及检验;水压试验;锅炉附件;烟风道及燃(物)料系统安装;脱硫、脱硝、灰渣系统安装;筑炉、防腐、保温;高温烘炉;化学清洗;启动试运行;交工资料等。
本规范由中国石油化工集团公司负责管理,由中国石油化工集团公司施工技术广州站负责日常管理,由中石化第五建设有限公司负责具体技术内容的解释。执行过程中如有意见和建议,请寄送日常管理单位和主编单位。
本规范日常管理单位:中国石油化工集团公司施工技术广州站
通讯地址:广州市荔湾区中山七路81号邮政编码:510145 电话:020-28348176 传真:020-28348169
本规范主编单位:中石化第五建设有限公司
通讯地址:广州市荔湾区中山七路81号邮政编码:510145
本规范参编单位:中石化宁波工程有限公司本规范主要起草人员:南亚林王永红张永明 李军利 常志勇 杜红斌 高小兵 韩跟平
马靖
本规范主要审查人员:张奉忠周家祥葛春玉 许永伟 孙桂宏 苏延秋
本规范为首次发布。
VII