AP1000依托项目多项目管理的质量保证体系建设
赵良磊
(国核工程有限公司,上海200233)
摘要:作为三代核电技术引进、消化、吸收的载体,AP1000依托项目质量保证体系面临着多项目并行,多质量保证标准适用,多业主监管的实际情况。通过质保大纲及程序文件的建设和优化,AP1000依托项目逐步建立了完整质量管理体系,保障了项目的顺利推进。
关键词:AP1000依托项目:多项目:质量保证体系
中图分类号:TM623.8
文献标志码:B文章编号:1009-3230(2016)05-0004-03
MultiplexProjectQualityAssuranceManagementinAP1oo0
Self-relianceProject
ZHAO Liang -lei
(China Nuclear Engineering Company Limited,Shanghai 200233,China)
Abstract: As the organization of introduction, digestion, absorption for third generations of nuclear power technology, AP1000 self reliance projects quality management system is presented with multiplex projects, multiplex quality assurance standards and the multiplex owners"oversight. Through the establishment and optimization of quality assurance program, AP1000 self - reliance projeci
established the complete quality management system to ensure the project is progressing smoothly Key words: AP1000 self reliance project; Multiplex Project; Quality Assurance System
0引言
AP1000依托项目(简称依托项目)建设过程中,面临着多项目并行,多质量保证标准适用,多业主监管的情况,如何建立一个能够全面满足法规和业主要求的质量保证体系就成了无法避免的课题。
AP1000依托项目中的多项目管理在依托项目中,国家核电技术公司和三门核
电有限公司、山东核电有限公司作为联合采购方对外签署NI合同,并授权国核工程有限公司与两个业主分别签订EPC总包合同,组织西屋联队及
修订日期:20160401
收稿日期:201603-15
作者筒介:赵良磊,女,工程师,毕业于上海交通大学,硕土
研究生,现在国核工程有限公司从事质量保证工作。
万方数据
业主三方共同组成依托项目核岛联合管理机构(JPMO),负责项目的核岛工程设计、设备采购和工程建设,并承担质量、进度、安全、投资“四大控制”责任。
AP1000项目部
JPMO
SNPEC
西屋联合体 NI设计及部分设备供货
设备制造商
SPMO
建造承包商
图1AP1000依托项目管理模式