
48
D01:10.7672/sgjs2013120048
施工技术
CONSTRUCTION TECHNOLOGY
2013年6月下第42卷第12期
特殊地质条件下导流隧洞堵头封堵技术
周冠荣,金薇,吴栋
(武警水电第二总队第五支队,江苏常州
1213135)
【摘要】导流隧润的封堵施工是水利枢纽工程下闸蓄水后需立即实施的最后一个关键施工项目,其封堵的成功与否及效果好坏直接关系到水电站坝前库区的蓄水速度及厂房机组的发电出力大小。长潭河水利水电枢纽工程导流隧润永久混截土堵头在润内渗水产重、岩体较差等特殊地质条件下成功实施封堵并达到了预期效果,取得了良好的经济效益和社会效益。
[关键词】隧润;渗漏:排水;封堵
【中图分类号】TV551
【文献标识码】A
[【文章编号】1002-8498(2013)12-0048-03
PluggingTechnologyforDiversionTunnelUnder
Special Geological Condition Zhou Guanrong,Jin Wei,Wu Dong
( No. 5 Detachment, No. 2 Hydropower Force of Armed Police, Changzhou, Jiangsu213315, China)
Abstract: Plugging Technology for diversion tunnel is the last key construction projects need to bc immediately implemented after water storage in the water hydro-junction project. The plugging result is aeeea Changtan River hydro-junction project, the diversion tunnel is plugged successfully under the special geological conditions of bad rock strength and severe water leakage in the tunnel which gain good social benefit and economic benefit.
Key words:tunnels; leakage; drainage; plugging
1工程概况
长潭河水利水电枢纽工程总装机容量为2× 40MW。施工期采用过水围堰一次性拦断河床截流、隧洞导流的方式。导流隧洞为V级临时建筑物,布置于大坝左岸,洞身全长247.0m,过流断面尺寸为10m×12m,城门洞形,顶拱中心角120°。导流隧洞进口底板高程89.00m,出口底板高程87.00m;周围岩性为P青灰色、灰黑色含燃石条带灰岩夹泥灰岩,弱~微风化状,洞内节理裂隙、溶洞及层间错动等发育。仅在进洞口、出洞口采用混凝土各衬砌 20m,洞身全部采用钢筋挂网喷混凝土进行初期支护。根据设计在下闸前提供的地质资料:在0+ 000—0+080,0+080—0+140,0+1400+215段均存在库(河)水通过岸坡往润内的渗漏间题。
导流隧洞采用临时+永久相结合的方式进行封堵,进口处采用金属结构闸门临时封堵,洞身段【作者第介】周冠荣,技术员,E-mail;475190102@qq.com
[收稿日期】2013-02-26 万方数据
采用混凝土堵头永久封堵。永久堵头设计桩号0+ 116.65一0+131.65,总长15m,呈瓶寒状,采用 C20W8低热微膨胀混凝土,底部高程86.49m,顶部高程100.81m。堵头下游9m段在中间设拱形灌浆廊道,混凝土堵头浇筑完成达到一定强度后,在廊道内对堵头四周进行固结灌浆,并在堵头混凝土与原衬砌混凝土顶拱之间进行回填灌浆。
现场实地勘察情况 2
导流隧洞进口临时封堵的金属结构叠梁门下
闸后,意味着坝前库区开始正式蓄水,施工单位立即联合参建四方的相关人员到洞内实地勘察,发现堵头施工部位的裂隙发育,堵头上游侧的渗水较为严重。通过测算,堵头上游侧0+0000+106.65 段渗漏量约2717m/h,堵头段0+106.65—0+ 140.65段渗漏量约15m/h,堵头下游侧0+
140.650+255段约12m/h。施工特点及难点分析
1)堵头上游侧渗水严重,施工部位渗水量