唐山勒泰中心大跨度屋面单层网壳施工方案优选
高明德
(中铁城建集团北京工程有限公司,北京100024)
[摘要】对大跨度屋面单层网壳提出了整体提升和分块提升两种网壳安装方案,利用MIDAS/GEN有限元软件建立网壳屋面施工全过程仿真模型,得到不同方案下结构的力学响应,从质量控制、施工过程中结构受力等方面对比得到两种安装方案优缺点及适用性,最终确定整体提升方案为该工程采用,圆满地解决了工程难题,保证了工程进度及质量。
[关键词】钢结构;单层网壳;MIDAS/GEN;施工全过程;仿真
[中图分类号】TU758.11
【文献标识码]A
[文章编号】1002-8498(2016)10-0026-04
ConstructionSchemesSelectionofSingleLayerLattice
Shell in Tangshan Letai Center
Gao Mingde
(Bejing Engineering Company Limited of China Raileay Urban Construction Group,Bejing100024, China)
Abstract : Two construction schemes of single layer lattice shell in Tangshan Letai Center were proposed, namely integral elevating method and partitioning installation method. The simulation model of shell roof construction was establish with MIDAS/GEN, to obtain mechanical response of the structure under different scenarios. Two construction schemes were compared in terms of construction quality, mechanical status in construction process, advantages and disadvantages and applicability were given. Integral elevating method was adopted for the project with engineering problems solved, and met the project schedule and quality requirements.
Key words : steel structures ; single layer lattice shell ; MIDAS/GEN; construction process ; simulation
施工是结构逐步成型、荷载逐步施加的连续过程1]。对于复杂结构,其受力和变形更是与施工过程密切相关,应综合考虑多种施工方案,通过对施工安装全过程进行仿真分析,确定施工过程中及成型后各关键构件内力变化特点及规律,综合考虑施工过程中各方面影响因素,获得最佳施工方案。
单层网壳是典型的缺陷敏感结构,对施工过程中的变形控制和安装精度要求十分严格[2]。单层网壳在施工中儿种常见施工方法分别为高空散装法、整体提升法、分条分块安装法。
工程中通常由于建筑空间要求,网壳下部空间
直通地面,若采用高空散装法,则需在网壳下布置满堂架,脚手架用量大、经费高、工期长[3],同时安装精度及作业安全性无法得到保证,针对该类工程条件对比分析整体提升及分块提升两种方法,为后
【作者简介]高明德,高级工程师,E-mail391028219@qq-con[收稿日期]2016-01-05
续工程提供参考。
施工方案简介 1
1.1工程概况
唐山勒泰中心项目A区商业综合体屋盖为钢结构弯顶造型(见图1),净跨39m,高度27.5~ 34m。单层网壳外接环桁架,环桁架与下部混凝土结构通过6根钢树权柱连接,共同组成穹顶。
单层网壳环桁架
树权程
图1单层网壳结构
Fig.1 Single-layer latticed dome
1.2整体提升方案简介