石仓岭隧道渗漏水治理与施工
王成伟张世豪
(中交隧道工程局第三工程公司江苏南京211100)
2010年10月第39卷第10期
[摘要]针对石仓岭隧道渗漏水病害现状进行了详细地实地调查分析了病害成因提出了该隧道渗漏水的治理措施即堵漏、注浆及引流等同时根据不同渗漏情况提出了对应的施工工艺及要求。通过施工实践,该方案有效
地控制了石仓岭隧道的渗漏水情况缩短了施工工期、节约了施工成本,[关键词】隧道;渗漏水;施工技术
[中图分类号】U457*.2
[文献标识码】A
[文章编号]1002-8498(2010) 10-0102-03
Treatmentand Construction ofWaterLeakageinShicanglingTunnel
Wang Chengwei,Zhang Shihac
( The Three Engineering Company of CCCC Tunnel Engineering Co. Jad. , Vanjing , Jiangsu211100 , China)
Abstract: Based on the water leakage of Shicangling Tunnel , particular investigation is taken , and the leakage factors are analyzed. The treatment of water leakage is given , including plugging , grouting and drainage. According to different water leakage conditions , the corresponding construction technologies and requirements are introduced. Based on practical construction , the measures can solve the water leakage of Shicangling Tunnel. The construction period is shorten , and the construction cost is saved. Key words: tunnel; water leakage; construction technology
1工程概况
石仓岭隧道1997年建成通车隧道按一级汽车专用公路标准设计,净宽为10.25m,左洞为+2.68%上坡全长2014m;右洞为+2.69%上坡,全长2036m。隧道围岩原设计以V类为主少部分IV类衬砌结构设计采用新奥法原理·隧道防排水设计以堵(防)为主堵排结合对于洞口端的地表水果用以排为主排堵结合即采用防水层及弹黄官沟导水管两者结合防水层为复合式橡胶防水通过纵环向弹簧盲沟将水排入洞内侧沟。
2隧道渗漏水病害调查与成因分析 2.1隧道渗漏水统计
石仓岭隧道通车10多年来出现了不同程度的病
害依据公路水泥混士路面养护技术规范》JTJ 073.1-2001、(公路路基路面现场测试规程》JTJ059-95 以及改造工程的设计要求,对隧道的渗漏水病害进行了沿线调查、渗漏状况记录、分类统计,统计情况如下:①隧道衬砌施工缝及环向渗漏水,双线4877m;② 隧道变形渗水双线378m;(3)隧道衬彻点状渗水双线28处;④隧道施工缝、变形缝及衬点状涌流排水,双线1处;5隧道集中出水点排水双线24.8m;@隧
道不规则斜向裂缝渗水,双线2208.3m。隧道综合评价等级为1A级。
2.2渗漏水成因分析 2.2.1客观原因
1)石仓岭隧道二次衬砌大部分采用小模板施工,施工接缝较多。二次衬砌施工完成后,随着混凝土温度应力、收缩和徐变应力的变化衬砌接缝处出现微小装缝再加上长期恶性自然条件的影响裂逐渐扩展。
2)石仓岭隧道穿越的山体岩性为石灰岩、白云岩,节理裂较发育小型溶洞较多地下水通道畅通再加上沿线山区雨量大致使地表水补给充沛,岩溶、裂隙等地下水丰富、涌水量大造成隧道洞体周边有大量的水蓄积衬动承受的水压增大
3)山体岩性的主要成分是石灰岩(主要成分 CaCO,)致使隧道周围裂隙水中钙物质较多,造成了既有隧道排水系统特别是导水盲管和泄水孔的堵塞。 2.2.2主观原因