松散堆积体边坡锚索钻孔施工关键技术*
张德圣
(安徽理工大学土木建筑学院,安徽淮南232001)
【摘要】松散堆积体错索施工难度较大,技术含量很高,面钻孔施工是错索工程的前提和保证。对堆积体错索钻孔施工技术进行了系统研究。从锚索孔放样、施工平台搭设、钻机校正和定位、成孔技术以及孔斜检测技术等几个方面对错索钻孔的关键技术进行了分析和总结。
【关键词】边坡;松散堆积体;锚索;钻孔;检测;施工技术
【中图分类号】TV541
【文献标识码]A
【文章编号】1002-8498(2013)19-0092-03
Key Construction Technologies of Anchor Cable
Drilling in Loose Deposit Slope
Zhang Desheng
(School of Architecture and Civil Engineering, Anhui Unisersity of Science & Technology, Huainan, Anhui 232001, China) Abstract:lt is very dificult to construct anchor cable in loose deposit, it needs high technology, and borehole construction is the prerequisite and guarantee of the anchor cable project. This paper studied systematically on the drilling construction technology of anchor cable in the accumulation body alone. The author analyzed and summarized key construction technology of anchor cable drilling from anchor cable holelofting, construction platform setting up, drilling rig calibration and positioning, drlling technology as well as inclination detection.
Key words:slopes; loose deposit; anchor cables; drilling; detection; construction
目前,人们对堆积体错索施工技术的研究较多[19],但绝大多数研究偏向于整个锚索工程,单独对锚索钻孔施工的系统研究很少甚至没有,而锚索钻孔施工又决定着整个铺索工程的成败。本文以堆积体铺索钻孔施工为立足点,对钻孔施工中的关键性问题进行了详细和系统研究,并以此为以后的
锚索施工、设计和理论研究提供借鉴和参考。钻孔施工工艺流程
锚索钻孔施工工艺流程如图1所示。 2钻孔设备
铺索成孔过程中,多数是通过钻孔设备成孔,有的是预留孔道(如坝体锚索孔)。而锚索钻孔也有水钻和干钻之分,在弱风化较完整岩体或黏土体中钻孔可采用水钻;在堆积体和强风化破碎岩体中钻孔则宜采用干钻。在堆积体中钻孔若采用水钻,
*安徽高校省级自然科学研究项目(KJ2012Z076):安徽理工大学引进人才基金(2009YB12)
【作者简介】张德圣,博士研究生,副教授,E-mail;zhangdesheng7412@tom.co
[【收稿日期】2013-01-06 万方数据
镐孔放样孔斜检测
不合格纠偏
终孔验收
搭设钻孔平台跟管开孔钻进维续跟管钻进
合格
钻至设计孔深
移机就位校正、定位钻至基岩或孔壁自稳段改换常规钻头
钻进
图1
锚索钻孔施工工艺流程
Construetion process for anchor cable drilling
Fig.1
由于其自身的稳定性较差,会使得钻孔成孔难度加大甚至可能会导致堆积体失稳;而文中所提及的干钻主要是指锚固钻机利用风动压力钻进,避免了水钻带来的不利影响。因此,堆积体锚索钻孔设备主要是锚固钻机和空压机。
目前,市场上锚索钻机的种类有很多,但并不是每种锚索钻机都适宜在堆积体中施工。根据以往钻孔施工经验[1,7],堆积体铺索钻孔设备主要以 YG-80、重探MGY-80和MCY-100型潜孔钻为主;空压机以英格索兰电动空压机为主。