超高层核心筒混凝土水平楼板跃层施工技术
王建春,王开强,刘晓升,刘威,崔健,杨辉(中建三局集团有限公司技术中心,潮北武汉430070)
【摘要】针对深圳华润总部大厦项目中核心简施工不等高同步攀升导致水平楼板滞后较多的间题,利用贝雷架跃层施工水平楼板,并对该施工方法进行数值分析。研究结果表明,在不影响核心筒剪力墙进度的前提下,保证了水平楼板施工进度能够快速追上竖向墙体。
【关键词】高层建筑;顶模;楼板;贝雷架;施工技术
[中图分类号】TU745.1
【文献标识码】A
[文章编号】1002-8498(2016)09-0010-03
Jump-layerConstructionTechnologyofConcreteHorizontalFloors
in.CoreTube of a SuperHigh-riseBuilding
Wang Jianchun,Wang Kaiqiang,Liu Xiaosheng,Liu Wei,Cui Jian,Yang Hui
( Technical Center, China Construction Third Engineering Bureau Co. ,Lad. , Wuhan, Hubei 430070, China)
Abstract : In the Shenzhen Huarun Headquarters Building project,the bailey truss is firstly adopted in the jump-layer constuction of the horizontal floor. Numerical analysis of the construction method is carried out and the results show that the method can short the construction period between the horizontal floor and the
vertical shear wall without affecting the construction progress of the vertical shear wall of core tube. Key words:tall buildings;jacking formwork; floors;bailey truss; construction
1工程概况 1
华润总部大厦(又名华润春笋大厦)项目位于深圳市南山区后海湾,地上66层,地下4层,建筑总高度400m,主体结构核心简竖向墙体施工采用微凸支点智能控制顶升模架。核心筒竖向墙体施工期间,由于核心筒内的硬防护以及外简水平楼板未施工完成,安全无法保障且材料运输困难,导致核心筒内2层水平楼板一直未插人施工,导致后期竖向墙体与水平楼板施工进度相差达到11层(67.35m)。原计划水平楼板采用铝模快拆体系结合顶模同步施工的方案一直无法得到落实,因此需要进行高空跃层水平楼板施工,并赶上竖向墙体进度。
需要进行高空施工的楼板为4,6,8号筒结构以及中心部位楼板,其中4号筒楼板尺寸为11.50mx 1.80m,6号简楼板尺寸为11.45m×3.80m,8号筒楼板尺寸为8.25m×3.80m,中心部位(5号筒)楼板尺
*中国建筑股份有限公司“十二五”科技支撑计刘课题(2011BAJ09B04)
【作者简介】王建春,业务经理,工程师,E-mail:281178149@q9.com
【收稿日期】2015-07-01 万方数据
寸为3.40m×3.80m。计划施工楼层为12层楼板。 2施工方案
本楼板采用普通木模+钢管扣件搭设方案,计划在高空搭设贝雷架平台作为支撑模架受力体系。具体施工流程为:放线一→吊装贝雷桁架一→焊接平台 →搭设支撑模架→铺设模板→绑扎钢筋→浇筑混凝土。
2.1高空平台安装方案 2.1.1平台安装参数
高空平台受力骨架采用3000mm×1500mm× 176mm贝雷架安装,按照基本模数(900mm或 450mm组合)确定贝雷架布置间距为900mm或 1350mm,两榻贝雷架之间采用2[10进行斜向交叉连接。具体布置方式如图1所示。
桁架平台挂架安装完成后,在5,6,8号简桁架上方铺木方+模板(木方间距300mm),形成操作平台兼硬防护。在4号筒桁架上方先铺设I14(间距 1m),再在工字钢上方铺设木方+模板(木方间距
300mm),形成操作平台兼硬防护。 2.1.2平台吊装方法
吊装前,在贝雷架支点位置连梁上提前预埋