2010年6月第39卷第6期
施工技术
CONSTRUCTIONTECHNOLOGY
西龙池电站混凝土面板裂缝成因及防控措施
杨涛,唐经华
(武零水电第二总队,江西南昌
330096)
【摘要】基于山西西龙池抽水蓄能站工程,根据高陡边坡的混凝土面板设计和工程特点,检查混凝土面板裂缝状况。从面板结构设计、原材料、配合比、环境地质和施工等方面,对混凝土面板裂缝成因进行分析。同时提出混凝土面板裂缝的防控措施,包括设计、施工和养护等环节进行严格控制。经过采用有效的措施,控制了面板裂缝的发展,保证了施工安全和质量。
【关键调】水电工程;高陡边坡;面板施工;表缝防治
【中图分类号】TV73
【文献标识码]A
【文章编号】1002-8498(2010)06-0015-04
CrackCausesandPreventionMeasuresofConcrete
Panel in Xilongchi Hydropower Station
Yang Tao, Tang Jinghua
(No.2 Hydropower Force of Armed PoliceNanchang,Jiangxi330096,China)
Abstract: Based on the engineering of Xilongchi pumping storage, cracks of concrete panel are checked according to concrete panel design and engineering characteristics of high and steep slope. The reasons of concrete panel cracks are analyzed from panel design, original material and mix proportion as well as environmental geology &nd construction. At the same time, prevention and control measures are put forward, including design, construction and maintenance. As a result, development of panel cracks is controlled, which can ensure construction safety and quality.
Key words:hydropower project; high and steep slope; panel construction; crack prevention
1工程概况
山西西龙池抽水蓄能电站位于山西省忻州市五台县境内,漳沱河与清水河交汇处上游约3km处的漳花河左岸,电站装机容量为1200MW,年发电量为18.05 亿kW·h,上下库水头落差644m,目前是世界上仅次于日本葛野川电站的高水头电站,工程等级为I等, 2003年主体工程开工,工程建设总工期为6年。
西龙池下水库为建在深覆盖层基础上的岸边式水
库,由一座堆石坝和库岸围成。最大项高97m,总库容 494.2万m。库盆采用全库防渗,其中库内坝坡和库底采用沥青混凝土面板防渗,库岸为钢筋混凝土面板防渗,混凝土面板村砌总面积为6.85万m。
工程区域地处北方严寒地区,冬季气湿较低,冰冻期从11月下旬至次年3月上旬,年极端最高气温为 37.4℃,年极端最低气温为-27.9℃,最大冻土深为 117cm。
2混凝土面板设计 2.1面板设计参数
万方数据
15
西龙池电站下水库库岸边坡混凝土面板共122块(包括岸坡坡面相交处的7块趾板),沿库岸轴线方向累计宽约1055.3m,自右岸向左岸依次编为12个区,编号为YPQ1~YPQ12。
混凝土面板不设水平缝,只设垂直缝。面板设计宽度为6~12m;标准面板坡比为1:0.75;斜长为 66.8m,最大斜长为110.0m。面板混凝土设计强度等级为C25F300P8,法向厚度0.4m,其底部设C10无砂混凝土排水垫层,法向厚度0.3m,排水垫层表面设 0.8cm左右厚的水泥砂浆层。
面板采用单层双向配筋,规格为Φ22@200。为了面板的稳定,面板下设锚杆将面板及面板下无砂混凝土错固于高陡岩坡上,锚杆规格为Φ28mm,间排距为 2m,错杆锚人基岩的深度根据基础地质状况分别为3
【收稿日期】2007-12-17
【作著禽介】杨涛,武警水电第二总队高级工程师,江西省南晶市高新区艾溪潮三路330096,电话:13607900296,E-mail: wjgcjsk@ 263. com