doi:10.3969/j.issn.16715152.2014.02.005
叶彩花等·燃气冷热电联供分布式能源系统中发电机组选择的分析探讨
燃气冷热电联供分布式能源系统中
发电机组选择的分析探讨
口北京燃气能源发展有限公司(100101)叶彩花白一乔丽洁
摘要:燃气发电机组是燃气冷热电联供分布式能源系统设计中最关键的部分,发电机组选择的合适与
否直接决定三联供项目的成败。本文详细分析了燃气发电机组容量确定的几种方式以及判断发电机组配置是否合理的几种指标,为燃气冷热电联供分布式能源系统发电机组的选择提供借鉴。
关键词:燃气发电机组燃气冷热电联供分市式能源系统以热定电以电定热满负荷时数
ResearchonOptimumSelectionofPowerEquipmentinDistributed
EnergySystemCombinedCoolingHeatingandPower
Beijing Gas Energy Developments LTDYe Caihua, Bai Yi, Qiao Lijie
Abstract : Gas generator set is the most critical part of the distributed energy system design. The appropriate choice of
generator set determinesthe key ofproject, This paper concretely analyzes several methods for the selection of generator capacity andsome indicators of generatorallocation, which will provide reference for the optimization of gas generator set.
Keywords:gas generator set
distributed energy system combined cooling heating and powen
ordering power by heat
tordering heat by power
引言 1
2011年国家四部委下发《关于发展天然气分布式能源的指导意见》,意见中指出“十二五”期间建设1000个左右天然气分布式能源项目,并拟建设10 个左右各类典型特征的分布式能源示范区域。到2020 年,在全国规模以上城市推广使用分布式能源系统装机规模达到5000万kW,初步实现分布式能源装备产业化。”2013年2月27日国家电网发布《关于做好分布式电源并网服务工作的意见》,解决了发电并网
万方数据
fullload hours
的行业壁垒。随着国家对燃气分布式能源项目的支持,越来越多的项目计划采用燃气分布式能源供能方式,但是如何合理的设计分布式能源项目,使建成的分布式能源项目真正实现效率最高,经济最优,是目前呕需解决的问题,而对于燃气分布式能源项目中最关键的设备燃气发电机组的合理选择是项目成败的关键,本文详细分析了燃气发电机组容量确定的几种方式以及判断发电机组配置是否合理的几种指标,为燃气冷热电联供分布式能源系统发电机组的选择提供借鉴。
2014/02总第468期121