
116
DOI:10. 7672/sgjs2017030116
施工技术
CONSTRUCTIONTECHNOLOGY
2017年2月上第46卷第3期
人工顶进双钢管穿越河道抱管分析及处理方法
康建新,王春丽,肖斌,仇伟,翟红,尹德胜,曹磊
(北京城建亚泰建设集团有限公司,北京100013)
[摘要】西南热电中心配套热力管线工程草桥电厂一京开高速柳村路段12~13号节点穿越暗河河道时回水管线发生抱管,无法单方向继续顶进,为解决此问题,采取了对接顶进,并取得了很好效果。通过对此事件进行分析及处理,重点介绍地下管线人工对接顶进的施工方法。
【关键词】隧道工程;热力管线;人工项管;抱管;分析;处理
[中图分类号】U455
【文献标识码】A
【文章编号】1002-8498(2017)03-0116-03
HoldingPipeAnalysisandTreatmentMethod of Manual Jacking
DoubleSteelPipeCrossingRiverChannel
Kang Jianxin,Wang Chunli,XiaoBin,QiuWei,Qu Hong,YinDesheng,Cao Lei
(Beijing Urban Construction Yatai Group Co.,Ld., Beijing100013, China)
Abstract:When Southwest Thermoelectric Center supporting pipeline engineering No. 12 ~ No. 13 joint crosses through underground river, the holding pipe happens for return line, so it can not be single direction jacking. In order to solve this problem, by docking jacking, and it achieved good results. Through the analysis and processing of this event, this paper focuses on the construction method of the underground pipe jacking construction method.
Key words:tunnels;heat pipeline; manual jacking; holding pipe; analysis; treatment
1工程概况
西南热电中心配套热力管线工程(草桥电厂一
京开高速柳村路)12~13号节点管线长92.5m,位于角门路南侧,世界花卉大观园西侧的道路上,自西向东穿越现状暗河河道(见图1a),设计为顶双套管过河施工,间距3.8m,管材为钢管,管径 2220mm,管壁厚为38mm,每节管长4m,管道续接接口为满焊。
暗河河道上口宽30.6m,下口宽18m,为方砖护砌,常年流水,水位2m左右,管顶距河底较近,约 5.5m,施工时易发生渗漏、涌水现象;且顶管位于砂卵石层(见图1b),地质结构呈颗粒状,围岩松散、稳定性差,易。为防止发生渗漏水和塌事故,施工前先对河道进行围堰截流及防渗处理,项管前
再对掘进面土体进行深孔注浆预加固处理。 2顶管抱管情况
管道从回水管开始顶进施工。进尺约53m时出现阻力增大现象,采用2台320t顶镐,管道未能[作者简介】康建新,项目经理,E-mail:262988410@q9.com
【收稿日期】2016-08-03 万方数据
顶进,钢后背由于反顶力的作用,发生弯曲无法顶进。此时,回水管顶管管头高程及中心偏差:横向位置向南偏移2cm,高程比设计高出1cm。如图2 所示。
3原因分析
3.1现场土质情况
顶管内上方150°范围内为卵石层,存在最大粒径≥10cm的卵石,管道上方卵石层的大粒径卵石掉落,随顶管顶进时,夹杂在管道和经过注浆加固后
的土体之间,卡紧管道,难以顶进。 3.2顶进过程中停止时间过长
由于续接管道焊缝焊接时间较长(>12h),管体受土体黏聚力的作用,导致卵石与管道之间阻力增大,管道被抱死,难以顶进。
4采取措施 4.1增加顶镐
重新加工钢后背,并增加2台350t顶镐,合计4 台顶镐,2台320t,2台350t,进行顶进施工,每台顶顶力达到350t(3500kN)时,套管仍然无法顶进。