苏丹某办公楼屋面高耸钢针安装方法
付国平,于志国
(中国江苏国际经济技术合作公司,江苏南京212008)
【摘要】介绍了苏丹首都喀土穆PDOC办公楼屋顶高耸装饰锅针的施工方法,在施工场地狭小和无大型起重设备的情况下采取将钢针分段加工,利用井字支架挂平动翻芦的方法进行分段吊装,步步顶进,使钢针在出井字支架之前完成其上所有的安装工作,避免了施工人员高危作业。该方法解决了多、高层结构屋面上装饰高耸结构的施工难题,并且具有良好的社会、经济效益。
【关键词】高聋结构;井字支架;钢针;起重设备;垂直度调节装置;倾斜导向轨道
【中图分类号】TU758.1
【文献标识码】A
【文章编号】1002-8498(2011)08-0045-03
InstallationMethodofToweringSteelPinonSomeBuildingRoofinSudan
Fu Guoping, Yu Zhiguo
(Chine Jiangsu International Economical & Technical Cooperation, Nanjing, Jiangsu 212008, China)
Abstract:Installation method of towering steel pin on the roof of PDOC office building located in Khartoum, Sudan is introduced at the condition of without sufficient working platform and heavy elevating equipment. Steel pin is manufactured by subsections and derrick hanging manual calabash is adopted for segment lifting. Installation work of steel pin is finished before out of the derrick which avoid aloft work. Through the practice, problem as installation of tall decorative structures on multi-storey and high level buildings is solved, and social and economical benefits are obtained.
Key words: towering structure; derrick; steel pin; elevating equipment; verticality regulator; leaning guide rails
1工程概况
苏丹首都喀土穆PDOC办公楼由5方共同投资组建,致力于苏丹东南部72000km地区内油气资源的勘探、开发与生产。该工程为钻孔灌注桩,主体为钢筋混凝土板柱结构,地下1层,地面主楼15层,裙房3层,建筑面积38000m,造价6030万美元,工期26个月,工作内容包括设计、采购、施工、调试,建筑外观如图1所示。
建筑顶部设计有高算装饰钢针,位于主楼机房顶部66.25m处,是一渐缩变径管形高算细长结构,钢针截面顶端140mm×9mm,底端820mm×
16mm,斜长47.521m,垂直高度45.723m,与水平面成74.28°,安装在标高64.34m的预留钢筋混凝土
结构基坑中,钢针自重6.841t,如图2所示。 2施工难点
受附着条件及塔身自由高度限制,现场塔式起【收稿日期】2010-05-29
【作者简介】付国平,中国江苏国际经济技术合作公司高级工程师,
江苏省镇江市江苏大学(本部)1区4栋406室
(0511)88780929,E-mail:jsfgp@163. com 万方数据
212013,电话:
图1建筑外观
Fig.1 Building appearance
45
重机有效工作高度75.0m,而钢针顶标高 110.063m,屋面标高66.25m,塔式起重机只能将钢针安装用的单元构件运输至钢针安装基坑边,钢针安装位置工作面狭窄,无场地安装一些起重设备和搭设满堂脚手架。若从下层屋面开始措满堂脚手架至钢针顶标高,钢针安装就位完全在高空条件下施