2018年第1期(总第241期)
doi:10.3969/j. issn. 1009 3230.2018. 01.006
应用能源技术
色议煤石综合利用电厂的脱硫问题
赵艳翠
(京能(赤峰)能源发展有限公司,内蒙古赤峰024007)
摘要:文中对当前煤研石综合利用电厂脱硫中的相关问题进行分析与探讨,对于湿法脱硫工艺中所常见的问题加以阐述,并指出相应的解决措施,如在循环流化床锅炉中炉内脱硫率较高,对于低硫煤产区应选择单纯炉内脱硫方式在高硫煤地区采用炉外烟气脱硫方式,对于燃料含硫较高的可以将炉内脱硫和炉外脱硫相结合。在煤研石综合利用电厂中应选择炉外烟气脱硫方式,同时还要根据硫含量具体多少来选用不同脱硫工艺。
关键词:煤研石综合利用电厂;脱硫工艺;炉内脱硫;炉外脱硫中图分类号:TK229.4
文献标志码:B文章编号:1009-3230(2018)01-0019-03
Discussion on theDesulfurization ofPowerPlantbyCoal Gangue
ZHAOYan-cui
19
(Beijing (Chifeng) Energy Developments Ltd,Chifeng 024007, Inner Mongolia Province, China) Abstract: Based on the analysis using the related problems in the power plant desulfurization and discuss the current comprehensive coal gangue, for the common problems in the wet desulfurization process are introduced, and points out the corresponding measures, such as in a circulating fluidized bed boiler furnace desulfurization rate is higher, the desulfurization way simple fumace for low sulfur coal producing area; the furnace the outer flue gas desulfurization in coal area, for fuel with high sulfur content can be fumace desulfurization and desulfurization combination. In the coal gangue comprehensive utilization of power plant, the method of flue gas desulfurization outside the furnace should be selected. At the same time, different desulphurization processes should be selected according to the specific sulfur content.
Key words: Coal gangue comprehensive utilization power plant; Desulphurization process; Desul-phurization in fumace; Outside fumace desulphurization
0引言
由于当前我国煤研石综合利用电厂普遍采用的锅炉炉型较小,且数量多,在脱硫过程中经常需要停炉检修,检修工作十分频繁,因此在脱硫工艺选择中应根据电厂实际情况,面循环流化床锅炉是电厂广泛采用的设备,其炉内脱硫率较高,当燃料含硫分较低时可以在炉内加钙,就可以提高其
收稿日期:2017-10-11
修订日期:2017-12-10
作者简介:赵艳翠(1988-),女,学士,研究方向为电厂
股碱。
万方数据
脱硫率,并实现排放达标["]。因此对于低硫煤产区在脱硫工艺选择中可以选择单纯炉内脱硫方案。而对于高硫煤地区则可以将炉内脱硫与炉外脱硫相结合,提高脱硫率。但不论是何种脱硫工艺的选择电厂都需要根据自身实际情况,考虑到经济合理性与投资可行性等方面的因索,提高脱硫效率。
循环流化床锅炉脱硫特点及问题 1
循环流化床锅炉脱硫工艺中炉内脱硫率较高,在炉内脱硫中加人脱硫剂,如石灰石,将其熳