CONSTRUCTION TECHNOLOGY
襄樊汉江三桥桩基施工技术
吴刚,张晋华,骆良
(中建三局股份公司工程总承包公司,潮北武汉430064)
【摘要】襄类内环线汉江三桥主桥为双塔、双索斜拉桥,其承台桩基为直径2m、长75m的C30混凝土钻孔满注桩。针对该桥水中桩基地质复杂及桩长较长的工程特点和难点,通过试桩工程试验,总结了相应的施工工艺与技术措施,如钻机选择、泥浆配备、钻进过程控制、混凝土灌注等。施工结果表明,经过成桩检测,主桥承台桩基全部达到1 类桩标准,基质量符合设计及相关规范要求。
【关键调】桥梁工程;斜拉桥;试桩;桩基础;施工技术
【中图分类号】TU473.1;U445.57
【文献标识码]A
[文章编号】1002-8498(2012)23-0037-05
ConstructionTechnologyofPileFoundationfor
Xiangfan Hanjiang the Third Bridge
Wu Gang,Zhang Jinhua,Luo Liang
(General Contract Company of CCTEB,Wuhan,Hubei430064,China)
Abstract: The main bridge of Hanjiang the Third Bridge is cable-stayed bridge with double towers and double cables,of which the pile foundation of pile cap is C30 concrete bored pile with 2m and 75m long. According to the engineering characteristics and difficulty that geological conditions of pile foundation is complicated and pile length is long, through engineering test for test pile, the authors summarize construction technology and technical measures, including drill selection, mud equipping, control of drilling process,concrete pouring and so on.Practice shows that pilefoundation quality of pile oaaaeaaaaaseessaeee Key words:bridges; cable stayed bridges; test pile; pile foundations; construction
1
工程概况
襄樊内环线汉江三桥主桥为双塔、双索斜拉
桥,主桥29,30号主墩桩基位于水中,桩基为直径 2m、长75m的C30混凝土钻孔灌注桩,按摩擦桩设计,其地质情况为:覆盖层为松散粉砂层,往下为中密卵石层、强风化泥灰岩、半成岩泥岩。29,30号主墩桩基桩位布置及地质柱状图如图1,2所示。
2桩基工程特点 2.1地质条件复杂
除桩基位于水中外,从地质柱状图可以看出,桩位处上部分为粉砂层和卵石层,钢护筒必须穿过粉砂层并进人一定厚度的卵石层才能保证钻机顺利钻进,同时钻进过程的泥浆指标及钻进速度也是
保证不孔的关键控制措施。 2.2桩基长度长
桩基设计长度为75m,对基成孔的垂直度及【收稿日期】2012-04-12
[作者简介】吴例,工程师,E-mil;wg99990@163.com 万方数据
00061
?
19.000
?@?
? 7?@
④ 000?
?
3005 00050005 00020c
图1
桩位平面布置
Fig.1Plan layout of pile position
37
沉殖厚度控制要求较高(本工程成孔垂直度为≤ 1/200,沉殖厚度≤10cm,均高于规范要求),必须选用相适应的钻机及采取合理的施工工艺,并进行严
格的质量控制。 3试桩工程试验 3.1试桩目的
水上桩基工程试桩,在汉江南岸滩进行,其目