超高层钢结构支撑架柱脚底座施工技术
王伟,孙伟波,陈诚,邓世强,吴慧琳
(中建三局集团有限公司,湖北武汉430000)
[摘要】华创国际广场1号塔楼为钢管混凝土柱-框架剪力墙结构,钢管混凝土柱预埋错栓的施工质量直接影响到整个钢结构工程。因此可靠的支撑形式以及切实可行的测量控制方法是保证满足预埋锚栓的精度和在浇筑混凝
土时埋件要求的关键技术。详细叙述了柱脚底座的节点构造和施工工艺。【关键词]钢结构;柱脚;锚栓;支撑架;底座
[中图分类号】TU758.11
【文献标识码]A
[文章编号】1002-8498(2014)08-0038-03
Construction Technology on Column Foot Bottom Support
in Super High-rise Steel Structure
Wang Wei,Sun Weibo,Chen Cheng,Deng Shiqiang,Wu Huilir
( China Construction Third Engineering Bureau Group Co. ,Ld. , Wuhan, Hubei 430000, China)
Abstract:The No.1tower building in Huachuang International Plaza is RC column-frame shear wall structure. Construction quality of the embedded bolts in RC column is key factor for the whole steel structure.Reliable support form and feasible measuring method are thekey techniques to meet precision of embedded anchor bolt and the embedded parts in pouring concrete. This paper shows in detail joint structure and construction technology of column foot bottom support.
Key words:steel structures; column foot; anchor bolt; supports; bottom support
1工程概况
华创国际广场1号楼地下4层,地上66层,总高度288m。主体结构采用钢骨混凝土柱-框架剪力墙体系,钢管柱落于3m厚筱板上,钢管柱截面尺寸为 Φ1600×40,共18根。每根圆管柱柱脚为30根长1 800mm,质量为27.76kg的M50螺栓,钢柱埋件(锚栓支架、锚板等)钢材材质采用Q345B,如图1所示。 2工程重点与难点分析
1)锚栓、锚板及支撑架安装过程中的测量控制难度较大,支撑面标高误差控制在±3mm。
2)每根圆管柱柱脚由30根M50螺栓组成,施
工时须保证所有铺栓均能顺利穿人错板,对每根错
的垂直度偏差精度要求高,规范要求锚栓安装时应无倾斜,支撑架的精度及稳定性直接影响到锚栓的施工质量。
3)在底板混凝土中预埋柱脚螺栓,不仅要求锚栓安装达到无倾斜,且对锚栓及锚栓支架具有高稳定性,保证在3m厚筏板浇筑混凝土过程中,锚栓及
[作者简介】王伟,助理工程师,E-mail:253676179@qq-com[收稿日期]2013-12-02
图1柱脚底座结构示意
Fig.1 Support structure on the column foot
锚板的位置中心偏差不超过5mm。
4)1号楼筱板底部为4排36钢筋,单根9m 长、36钢筋重72kg,需两人合力搬运。
5)1号楼工期紧,因此预埋锚栓及其支撑架的插人施工时间与筱板钢筋绑扎之间的施工顺序安排是否合理直接影响施工进度。