北京财富中心写字楼超高层钢结构施工技术
汪道金,苏建成
(中国新兴建设开发总公司,北京
100036)
【摘要】以北京财富中心写字楼工程为例,介绍了钢结构施工技术在该工程的应用。从深化设计、加工制作、运输及堆放、安装、测量及校正、焊接等几个方面对组合钢板墙的施工进行了详细的阐述。最后对高层及超高层建筑钢结构施工中的一些注意要点进行了总结。
【关键词]高层建筑;钢结构;组合钢板墙;深化设计;焊接;施工技术
[【中围分类号]TU758
【文献标识码】A
【文章编号】1002-8498(2013)01-0024-03
Construction of the Super High-rise Steel Structure of
BeijingFortune Plaza Wang Daojin,Su Jiancheng
( China Xinxing Construction & Derelopment General Co. , Bejing 100036, China)
Abstract: This paper introduces the application of steel structure construction technology in Fortune Plaza, Beijing. The construction of composite steel plate walls was introduced in detail from multiple aspects of detail design, manufacturing, transportation and stacking, installation, measurement and correction, welding, etc. At last, this paper summarized some points worthy of attention in steel structure construction of super high-rise building
Keywords: tall buildings;steel structures;
compositesteel platewall;detail design;
welding; construction
1工程概况
北京财富中心写字楼二期工程位于朝阳区东三环北路,地下4层,地上63层,标准层高4.18m,建筑高度264m,总建筑面积17方m,总用钢量约 3万t。结构体系为框架-核心筒混合结构。外框为钢管混土柱与钢框架梁组成。核心简为型钢混凝土柱和混凝土钢板剪力墙组成。4~20层剪力墙墙体厚度1200~1500mm,墙体中间采用整体全熔透焊接钢板墙作为钢骨,东西方向钢板墙宽15.1m,南北方向钢板墙宽3~5m。核心筒暗柱、暗梁、钢板墙连接节点采用全熔透焊接,钢材采用Q345GJC,钢板厚度为35,50,80mm3种型号,焊缝形式为单面坡口全熔透一级焊缝,两侧绑扎钢筋,墙体混凝土
为C60自密实混凝土。 2钢结构施工技术
2.1混凝土钢管框架柱吊装
为了减少现场钢结构的焊接量,方使运输及减
少塔式起重机的工作量和保证框架柱的安装质量,【作者简介】汪道金,总工程师,E-mailixvdj310@sina.com
【收稿日期】2012-11-26 万方数据
根据构件质量和塔式起重机的起重能力,本工程框架钢柱按照3层1节的方法分段吊装,个别超重规
格的钢柱按照2层1节,甚至1层1节来划分。 2.2钢板墙施工
在北京财富中心写字楼工程中,结构核心筒为
整体式钢板混露土剪力墙结构,剪力墙的钢板安装、校正及焊接难度很大,在施工中需要对深化设计、构件加工和安装技术进行严格控制,主要方法如下。
2.2.1钢板剪力墙深化设计
1)钢板剪力墙深化设计包括钢板墙单元划分和节点设计,深化设计要方便现场吊装施工,并有利于减少现场焊接量和焊接变形控制。
2)单元划分要考虑楼层层高、构件运输尺寸限
制、塔式起重机起重能力和吊装效率等因素,每节钢板墙钢骨柱以跨越3个标准层为宜,高度12 15m;钢板剪力墙由于平面外刚度较小、吊装时易变形,按每层高度设置施工段,高度以4~5m为宜(见图1)。
3)节点设计要保证钢板剪力墙吊装精度,钢板