2015年6月下第44卷第12期
D01:10.7672/sgjs2015120105
施工技术
CONSTRUCTION TECHNOLOGY
混凝土防渗墙围堰体加高防渗技术
童耀
(葛洲坝集团基础工程有限公司,湖北宜品
443002)
【摘要】乌东德水电站左岸导流隧洞出口围堰在汛期过水后受损,需进行二次围堰填筑与防渗处理。筒要介绍了该工程采用石硅回填加高受损混凝土防渗墙围堰体后,采用高压喷射灌浆进行防渗处理的施工技术。工程实践表明,该方法可有效缩短工期、减少成本,达到了快速、高效地修复受损混凝土防渗墙围堰体的目的。
【关键调]混凝土:防渗墙;图堰体;施工技术
【中图分类号】TU753.62
【文献标识码】A
【文章编号】1002-8498(2015)12-0105-04
Anti-seepage Technology of Anti-seepage Concrete
WallbyHeighteningCofferdam
TongYao
( China Gezhouba Group Foundation Engineering Co. ,Lid. , Yichang,Hubei 443002,China)
Abstract; The cofferdam which is located at the exit of diversion tunnel on the left of Wudongde Hydropower Station is damaged after the flood season, it must be filled in second times and do anti-seepage treatment. After the cofferdam of the anti-seepage concrete wall is heightened with stone ballast, the high pressure jet grouting is applied to do anti-seepage. The practice shows that this method can reduce the construction period, save the construction cost, and the anti-seepage aim is achieved rapidly and effectively by heightening the cofferdam.
Key words:concrete;anti-seepage wall;cofferdams;construction
随着水电开发深度的不断增加,建坝条件越来越复杂。尤其是重点建设的西部水电站地处高原,山高谷深、水滞峡长者居多,对挡水防渗围堰性能的要求越来越高。在挡水防渗围堰度汛后,存在防渗围堰体受损需进行加高防渗处理的情况。从工期、质量、经济等方面综合考患,采用在混凝土防渗墙体上接高高压喷射灌浆防渗体的施工方法,能达到快速、高效地加高挡水围堰体的目的。本文结合作者的工程实践及施工经验,对混凝土防渗墙围堰
体加高防渗施工技术进行了阐述和总结。 1工程概况
乌东德水电站以发电为主,兼顾防洪,施工导流采用河床一次截流、隧洞导流的方式,左岸布置2 条导流洞,出口均与电站尾水结合;右岸布置3条导流洞,其中2条出口与电站尾水结合。左岸导流隧洞出口围堰为枯水期临时挡水建筑物,堰顶高程为 828.5m,出口部位围堰采取混凝土防渗墙进行防渗
【作者简介】量级,高级工程师,E-mail:497648660@qq.com
【收稿日期】2015-01-17 万方数据
处理。
105
根据水电站2013年度汛技术要求,左岸导流隧洞出口围堰为过水围堰。在度汛期间,由于金沙江水位持续上涨,流量激增,导致左岸导流洞出口围堰临江侧出现沉降变形。当左岸导流洞出口水位达到832.23m、流量11200m/s时,围固堰堰体向江侧最大沉降变形达1.3m,并持续加大。为确保围堰的整体稳定,避免围堰受损的进一步扩大,实施了破堰充水,确保了汛期安全。但围堰ZWO+ 138.646—ZWO+337.067部分受到不同程度损坏,混凝土防渗墙沿轴线变形长度约200m。
为保证导流洞过流的目标工期,确保基坑内土建的安全施工,需对损毁的混凝土防渗墙围堰体进行二次围堰填筑加高及防渗处理。根据现场施工条件,围堰损毁段采用石碴料进行回填,厚度达到25m。
受损围堰防渗施工方案比选
2
在混凝土防渗墙体上搭接新的防渗体作为临时挡水建筑物,目前在国内尚无成功经验可循。为