上海青草沙水库围堤混凝土裂缝质量控制
罗小生,时国庆
(武警水电第二总队七文队,江西鹰潭335001)
【摘要】基于上海青草沙水库固堰混凝土工程,根据裂缝宽度,对混凝土裂缝进行分类和检查。同时根据裂缝特点,依次提出相应的解决办法。着重闹述裂缝化学谨浆的施工工艺,包括谨浆时间选择、谨浆孔的设计、布置原则以及钻孔冲洗等。通过检查验收认为,对不同裂缝采用相应的处理方法能够达到缺陷部位补强的目标,从而保证施工质量和安全。
【关键词】青草沙水库;混凝土工程;裂缝缺陷;施工技术
【中图分类号】TU62;TU755
【文献标识码]A
[文章编号】1002-8498(2010)06-0007-03
TreatmentonConcreteDefectofCofferdamin
ShanghaiQingcaoshaReservoir
Luo Xiaosheng,Shi Guoqing
(No. 7 Detachment, No.2 Hydropower Foree of Armed Police, Yingtan, Jiangxi 335001,China)
Abstract: Based on the concrete in cofferdam in Shanghai Qingcaosha Reservoir, the concrete cracks are classified and checked according to the width of concrete cracks. Besides, the corresponding solutions are put forward according to the characteristics of cracks. The construction technologies of crack chemical grouting are outlined, including selection of grouting time, design of grouting holes, arrangement principles and drilling washing. It agrees that the corresponding treatments are respectively adopted to treat different cracks, which can reinforce defect. Thus, it can ensure construction quality and safety. Key words: Qingcaosha Reservoir; concrete engineering; crack defect; construction technology
裂缝是混凝土工程中的常见缺陷之一,多由干缩、水泥水化热、荷载、温度、地基变形、冻胀等因素引起。若裂缝没有及时处理,则会进一步造成钢筋锈蚀等严重结果,是造成大体积混凝土破坏的主要原因。一般情况下,裂缝的处理难度比较大。目前水工混凝土的裂缝处理方法大致分为两类,即表面处理和内部处理
(指灌浆)。本文结合上海青草沙水库围堤工程,对这两类裂缝处理方法的工艺进行分析,为工程实践提供参考。
1工程概况
上海青草沙水库及取输水泵闸工程位于长江口长兴岛西北侧水域。南侧水域则为长江口南支南港河段,北侧水域为长江口南支北港河段。工程的主要功能是在非威潮期自流引水入库供水,在威潮期通过水库预薪的调蓄水量和抢补水来满足上海市的原水供应需求。青草沙水库如图1所示。
本工程新建一座北堤及上游取水泵闸,新建围堤中心线桩号10+466m~12+564m(含上游取水泵万方数据
图1青草沙水库
Fig.1 Qingcaosha Reservoir
闸),围堤长约2098m。上游取水泵闸位于青草沙水库新建北堤桩号12+262m处,为阐站结合布置方式(开散式闸型),水闸总净宽70m,单孔净宽14m,共5 孔。泵站设计流量200m/s,采用现浇混整土(地下连
续墙)结构。 2裂缝分类