工程建设与设计
tion&Duignferhyect
水利工程混凝土施工工艺控制措施 HydraulicEngineeringConcreteConstructionControlProcess
罗应军
(湖北大禹水利水电建设有限责任公司,武汉430060)
LUO Ying-jun
(Hubei Dayu Water Resources and Hydropower Construction Co.Ltd.,Wuban 430060,China)
【摘要】在我国国民经济的不断发展下,水利事业得到了快速的发展,国家对水利工程的入电越来越大,先后出现了各种大型水利建设工程,但是,在水利工程建设的过程中,混凝土工程的施工工艺控制措施一直是施工中的难点,对水利工程的质量有比较大的影响。基于此,论文通过实际策例对水利施工中混凝土裂缝的控制进行了探讨。
[Abstract Jwith the development ofournationaleconomy, waterconservancy has beenrapiddevelopment, the state of waterconservany project investment more and more, has appeared in various largescale construction of water conservancy project, However, in the process of waterconservancy construction, construction process control measures ofconcrete engineeringis always a difficult problem in the construction has great influence on the quality ofthe water conservancy project, Based on this, this article through the actual case control ofconcrete cracks in
water conservancy construction experienceis discussed in this paper.【关键词】水利施工;混凝土工艺;控制措施
【Keywords waterconservancyconstruction;concreteprocess;control measures
【中图分类号】]TV544
[文献标志码]B
[DO1]10.13616j.cnki.gjsysj.2014.12.023 1案例介绍
【文章编号】1007-9467(2014)12-0098-03
2工程施工特点
南苏丹Fula-Rapids水电站主要建筑物由挡水堰、引水渠、溢洪道及发电厂房等组成,设计流量350m%s电站装机2 台,装机容量为42MW。挡水堰工程需对填筑料上下游表面进行混凝土护面,及在堰体设置生态流放生设施结混凝土结构。厂房混凝土结由电站进水口使水流平稳从引水渠进人水轮机,进水口由闸墩和中墩及胸墙组成,长21m,宽43.5m,与厂房主机间等宽。厂房系统包括主厂房,上游副厂房,下游副厂房,进厂公路等设施组成。
【作者简介1罗应军(1978~),男,游北罗田人,工程师,从事水利水电工程设计与研究,(电子信箱)543800337@qq.com。
86 万方数据
1)施工工艺复杂。厂房工程结构形体复杂,孔洞、薄壁结构多,钢筋密集,埋件多;混凝土浇筑与机电埋件安装等相互制约。必须安排严密的施工工序和施工程序,采用先进的施工工艺、施工方法,充分利用新技术、新工艺保证施工质量和控制进度。
2)土建施工与水机、金结埋件安装平行作业多尾水管、锥管、前池及尾水闸门、进水闸、泄洪闸、冲渣闸等主要金结和机电埋件安装与混凝土施工平行作业。相互影响干扰大。
3)本工程枢纽工程混凝土施工部位多,施工区范围较分散,混凝土工程方量大(约4.3×10m),受控制性工期限制,前期施工月强度较高,故应合理布置施工机械及安排施工进度