焦炉用煤气调温的探索
来威吴秋阳冯云舒(鞍钢集团朝阳鞍凌钢铁有限公司,朝阳122000
July.2013 Vol. 44 No.4
摘要:高炉检修时,焦炉每年进行多次的煤气置换作业,通过分析置换煤气及炉温调整过程,确定优化方案,使置
换煤气时间缩短至2h,炉温调整时间缩短至5天。关键词:焦炉;置换煤气;调温
中图分类号:TQ520.5
文献标识码:B
文章编号:10013709(2013)04002403
Researchongastemperatureadjustmentforcokeovenbattery
Lai WeiWu QiuyangFeng Yunshu
( Anling Iron & Steel Co. Ltd. of Anshan Iron & Steel Group , Chaoyang 122000 , China )
Abstract: This paper analyzed adjustment for replacement gas and oven temperature for an optimal solution due to multi -time gas replacement for coke oven battery each year due to blast furnace main -tenance so that time consumption for gas replacement can be reduced to two hours and that for oven temperature adjustment can be cut to five days .
Key words: Coke oven battery ; Replacement gas ; Temperature adjustment
我厂有2座JN60-6型2×50孔复热式6m焦
炉。2*焦炉于2010年8月20日投产,1*焦炉于 2010年11月3日投产。由于我公司仅有1座高炉,高炉检修需进行频整的煤气置换作业,影响生产
的稳定运行。 1准备工作
1.1安全准备工作
在置换煤气作业前先联系消防车、救护车提前到达指定地点,当出炉停止后需保证焦炉炉顶无人,
置换煤气过程中不允许非作业人员穿行, 1.2人员条件
置换煤气时需调火班14人,煤气班6人,另外需当班倒班人员8人,并提前做好分工,具体分工见表1。
1.3设备条件
煤气管道安装打压完毕合格,无泄漏。机、焦侧高炉煤气加减旋塞清洗完毕,油杯上满油。动力风系统试验合格,风压不小于0.3MPa,无泄漏,保持良好。各处仪表和调节装置试验合格。高炉煤气孔板
收稿日期:2013-04-13
作者简介:来威(1974-),男,工程师
安装完毕,孔板盒保证无泄漏。开关加减旋塞工具准备齐全。地下室水封保持满流,放液管保持通畅,旋塞开关灵活。焦炉斜道正面密封完毕,保证无泄通。焦炉蓄热室封墙密封完毕,保证无泄浦。焦炉小烟道承插口密封完毕,保证无泄漏。废气系统运行平稳,行程准确,各设备无卡阻。进风门压板准备齐全。废气盘测温孔全部盖严。
表1人员分配
操作部位分烟道煤气压力表放散管废气盘地下室立火道地下室焦炉端台
人数
职责
2 2 2 8 8 2 2 2
1.4其他条件
按照要求调整分烟道吸力看高炉煤气主管末端压力表按指挥安排操作
机、焦侧各4人进行煤气进风门盖板操作地下室开关旋塞
在炉顶打开看火孔盖检查燃烧情况取样作爆发试验
佩戴好空气呼吸器,随时准备敦护
调节工具、通讯工具等应提前备好,提前3天联系专业抽堵盲板人员进行抽堵盲板作业,之前应先