Q/GDW 106182017代替 Q/GDW 618-2011
光伏发电站接入电力系统测试规程
Test procedures for photovoltaic power station connected to power system
2018-09-26实施
2018-09-26发布
目 次
前言..........................................................................1
1 范围............................................................................1
2 规范性引用文件 .............................................................1
3 术语和定义........................................................................1
4 总则..............................................................................3
5 测量设备..................................................................3
6 有功功率测试.....................................................3
7 无功功率测试......................................................................6
8 故障穿越测试....................................................9
9 频率适应性测试...................................................................13
10 电能质量测试.................................................................14
11 测试文件.................................................................15
附录A(规范性附录) 功率设定值控制响应时间及控制精度判定方法.....................16
附录B(规范性附录) 无功电流注入的判定及计算方法........19
附录C(资料性附录)测试记录...............21
编制说明..............................27
前 言
为规范光伏发电站接入电力系统,明确光伏发电站测试程序,保障光伏发电站接入后电力系统的安全、可靠运行,制定本标准。
本标准代替 Q/GDW 618—2011,与 Q/GDW 618—2011 相比,主要技术性差异如下∶
——增加了高电压穿越测试的内容;
——增加了一次调频测试的内容;
——增加了夜间静态无功输出特性、电压控制能力、功率因数控制能力测试的内容;
——删除了防孤岛保护特性测试、电压异常时的响应特性测试、通用性能测试的内容。
本标准由国家电网有限公司国家电力调度控制中心提出并解释。
本标准由国家申电网有限公司科技部归口。