某钢筋混凝土筒仓体外预应力加固技术
孙智,郭亚滨
(长春吉泰建设监理有限公司,吉林长泰130031)
【摘要】某钢筋混凝土简仓工程由于年久失修,质量无法满足使用要求,需要进行加固。通过分析,确定采用体外预应力加固法进行结构加固。结合工程实际情况,详细介绍了结构加固设计方案、施工流程和关键施工技术。通过对钢筋混凝土简仓体外预应力的加围施工,减小了简仓外壁规聚土的装缝宽度和变形,达到了设计规定的合理使用年限和储存容量。
【关懿调]加固;筒仓;钢筋混凝土:体外预应力;施工技术
[中围分类号】TU746.3
【文献标识码]A
【文章编号】1002-8498(2013)09-0053-04
External Prestressing Strengthening Technology
on a Reinforced Concrete Silo
Sun Zhi, Guo Yabin
(Changchun Jitai Construction Supervision Co., Lad.,Changchun,Jilin130031, China)
Abstract: An old reinforced concrete silo could not meet the requirements for normal operation and need to be strengthened. And after analysis, it was decided to use external prestressing strengthening mcthod. The design of the strengthening scheme, the construction process and key construction technology are introduced. The strengthening results showed that the crack width and deformation of outer wall concrete were decreased, and the silo could meet the requirements of specified service life and storage capacity Key words:strengthening; silos; reinforced concrete; external prestress; construction
1工程概况
某废弃多年的钢筋混凝土圆形筒仓原为储存散料的单体简仓。原始资料显示,简体混凝土设计强度等级C30,内径18m,简壁厚500mm,仓壁厚 350mm,高54m。经具有相应资质的检测机构鉴定,简壁混凝土强度和钢筋符合设计要求,仓壁30m以上混凝土强度偏低,钢筋闻距过大,钢筋保护层过厚。在筒仓西侧25~41m范围内有多道1~3mm 竖向裂缝,向外变形鼓胀,中心部位约1m范围的仓壁混凝土局部破坏,凸出最大处达280mm。
2
结构加固设计方案
本工程采用体外预应力施工技术,沿筒仓体外
圆周水平方向布置后张拉预应力筋,对筒仓进行预应力加固,外侧浇筑100mm厚混凝土护壁。预应力束为1×7Φ"15.2钢绞线,无黏结低松弛预应力钢绞线,抗拉强度标准值了=1860MPa,预应力张拉
智,高级工程师,总监理工程师,E-mail:1033138435
【作者简介】孙 sqq.c
[收稿日期】2012-11-13 万方数据
53
控制应力为αco=1395MPa,锚固体系为B&S系列
锚具,其配筋如图1所示。 3施工准备
3.1施工方案审批
体外预应力加固施工前,专业施工单位编制施工技术方案,需经设计单位认可签字后方可实施。 3.2材料构配件设备报审
1)对进场的材料构配件设备检查产品合格证、
出厂检验报告和质量证明文件。对砂、石、水泥、银筋进行见证取样送检复试,确定混凝土配合比,按设计要求做碱含量检测。
2)对预应力钢绞线进行抽检复试,其检测结果如表1所示。
3.3简仓检查测量
首先把筒仓顶部混凝土挑檐拆除,对筒体外形进行测量,检查其表面平整度和垂直度,为加固施工提供依据。
3.4脚手架搭设
1)按要求搭设双排脚手架,上人斜道,上料平