超长钢筋混凝土结构无缝抗裂设计和施工 No-seam Design and Constructionof Super-lengthConcreteStructure
柴传政,姚山,戴玲,翟继钊
(兰州军区空军勘赛设计院,兰州730020
CHAIChuan-zheng, YAO Shan,DAI Ling,ZHAI Ji-zhao(LanzhouAir Force Prospectand Design Institute,Lanzhou730020, China)
【摘要】利用高性能膨胀混凝土在结构中产生一定的预压应力来抵抗混凝土收缩变形产生的拉应力,从而防止或减小超长混凝土结构在施工阶段由于温度应力引起的收缩裂,通过合理布置膨胀加强带以取代后浇带,实现混凝土的连续筑,最终达到缩短施工工期和节省工程费用的目的。
[Abstract]Super-length concrete structure would he acted by large temperature stress in the varied temperature during construction, The stress could cause contracting cracks. To prevent or reduce contracting cracks of concrete plate, Prestress produced by high performance expansive concrete in structure is used to resist tensile stress in structure by concrete contraction Concrete plate can be casted continually due to setting up expansive reinforce concrete tape instead oflater cast concrete tape achievinggoals ofshorten construction period and cutdown thecost.
【关键词】超长钢筋混凝土结构;无缝抗裂设计与施工;高性能膨胀混凝土
[Keywords Jsuperlength concrete structure;noseam design and construction;highperformanceexpansiveconcrete
【中图分类号】TU757
[文献标志码]日
目前,越来越多的建筑结构向超大体积、超大跨度方向发展,这类结构的平面尺寸往往超过规范不设伸缩缝的限值。一般而言,设置伸缩终会增加设计难度,影响建筑物的立面效果;不设置伸缩缝会因施工或使用阶段的温差作用使结构产生收缩裂缝,直接影响结构的使用功能。为了解决设置伸缩缝所带来的一系列间题,对于此类结构往往采用设置后浇带的措施。但是,设置后浇带不能从根本上解决因温度收缩而产生裂缝问题,而且可能留下渗漏隐患。近年来,已有不少工程取消了伸缩缝而采用连续淡注混凝土方式并获得成功!。下面就超长钢筋混凝土结构无缝设计及施工的原理、方法和过程进行
【作者简介】荣传政(1971~),男,山东高密人,工程师,从事防护工程设计与工程项目管理研究,(电子信箱)yaoshan8@126.com。
118 万方数据
【文章编号】1007-9467(2013)11-0118-03 探讨。
1混凝土结构设计和施工中的缝”
混凝土结构设计中涉及的“缝”包括伸缩缝、沉降缝和防震缝,可统称为结构缝。其中沉降缝和防震缝分别与地基条件及构筑物的规则性有关,并不能通过构造或施工措施避免。伸缩缝是结构构造上的一种考虑,是基于混凝土干燥收缩和热胀冷缩而设置的,其中永久性伸缩缝(通常称伸缩缝)考患的是长期热张冷缩,临时性伸缩缝(通常称后浇带)考虑的是干缩和施工期间的水化热。
混凝土的施工缝是在混凝土浇筑期闻所形成的一种施工冷缝,包括水平施工缝,垂直施工缝和斜施工缝,和现场的施工条件和施工力量相关。施工缝在施工中应尽量避免出现,一旦出现必须及时处理。