高层建筑深基坑支护施工技术的研究
ResearchontheConstructionTechniqueofDeepFoundationSupport
in High-Rise Building
万佳琪
(中建一局集团第五建筑有限公司,北京101199)
WAN Jia-qi
(China Construction First Group the Fifth Construction Co. Ltd., Beijing 101199, China)
【摘要】目前,深基坑支护施工目前发展迅速,是高层建筑施工中的重要技术手段,可以有效地提高高层建筑的施工质量。论文介绍了高层建筑深基坑支护的类型,深基坑支护的施工技术,以及在深基抗支护施工过程中需要注意的问间题,以供参考。
[Abstract]At present,the supporting construction of deep foundation is developing rapidly, and it is an important technical means in high-rise building construction. It can effectively improve the quality of high-rise building construction. This paper introduces the types of deep foundationpit suppo,theconstructiontechnologyofdfoundationit support,and theproblemsneeding atentionintheonstruction deepfoundation pit support,forreference
【关键词】高层建筑;深基坑支护;施工技术;研究
[Keywords Jhigh-rise buildings; deep foundation pit support; construction technology; research
【中图分类号】TU753
【文献标志码]B
[DO1]10.13616/j.cnki.gcjsysj.2017.11.112 1引言
深基坑支护与高层建筑的施工安全和质量有直接关系,其施工难度较大,因此,要提高高层建筑的施工质量,就要对高层建筑深基坑支护施工技术进行研究,并把握先进、可靠的施工技术。
2高层建筑深基坑支护的类型 2.1钢板桩支护
用带有锁口、钳口的热轧型钢可以制成钢板柱,将它们相互连接就有了钢板墙,主要用来挡土和挡水。现在运用比较广泛的钢板柱的截面形式有U型、Z型和直腹板形。开始打柱前,要检验并校正钢板柱的质量。导架和围擦柱间的间距要符合标准,与钢板桩墙相比,双面围擦的间距要在8~15m,以便实现打柱的精度控制。插柱时,用吊车将钢板桩吊到插柱处,【作者简介】万佳琪(1983~),男,黑龙江齐齐恰尔人,工程师,从事
土木工程施工管理研究。 24
万方数据
【文章编号】1007-9467(2017)11-0024-02
并且要对准锁口,为了保证钢板桩的垂直度,在每插人一块钢
板桩后,要套上柱帽进行锤击。 2.2地下连续墙支护
地下连续墙指的是在泥浆护壁下的钢筋混凝土墙体,要分槽段进行施工。其技术、施工方法和机械都在不断地发展演变,现在的地下连续墙在基坑施工和拟建主体的结构中都起到了围护作用,如果施工方法和支撑措施正确,还可以实现对
软土地层变形的控制。 2.3锚杆支护
错杆支护是主动加固岩土稳定性的一种技术,锚杆的一端要稳定地探人岩体中,而另一端要施加预应力,连接支护结构,最终实现深部地层潜能的调动,这样就可以保证基坑的稳定性。另外,锚杆支护有较强的适用性,受基坑深度的影响小,有较强的适用性
2.4复合土钉综合支护
这一技术不仅经济实用,而且可以快速施工,是土钉墙和