临江深基坑支护与降水施工技术的应用
帅伟
(杭州市富阳区水利水电局,浙江富阳
311400
Vol.29Na.1 Feb.2017
摘要:临江河深基坑支护与降水等关键环节能垦著影响基坑外国的建筑物充其是江河提防的穗固与否.以富春江三山提加图工程为例,根据水文、地质地形条件,通过计算,采用拉森IV型钢板性支护,同时采用在钢版性外侧设并点降水,基坑内设深井降水进行联合降水,并落围照脚设置排水沟,并做好围堆的防渗处理工作.该工程技术在应用中效聚良好
关键词:临江深基疏:基坑支护;降水
中图分类号:TV551
文献标志码:A
文章编号:1008536X(2017)02-0045-05
EngineeringTechniques ofSupportingandDewateringfor
Riverside Deep Foundation
SHUAI Wei
( Fuyang Water Conservancy and Hydropower Bureau of Hangzhou, Fuyang 311400, China)
Abstract: The supporting and dewatering of riverside deep foundations are obviously significant to the steadiness of build ings outside the foundation ditch as well as the dike. Based on the dike reinforcement case of Sanjiangdi in Fuchun River according to the hydrological and geological conditions, the engineering technology is introduced by supporting with IV-shaped steel sheet pile and well-pointed dewatering outside the pile, combining with deep-well dewatering in foundation
ditch and draining in cofferdam with perfect anti-seepage treatment, which is proved to be considerably effective. Key words : riverside deep foundation; pit supporting; dewater
富春江治理工程——三山堤加固工程(金家桥排涝闸站)位于河道出口处,距富春江主流段约 100m.金家桥排涝闸站设计排水标准为30年一遇,闸站主体建筑物防洪标准为为30年一遇设计, 100年一遇校核.闸排流量58.5m/s,设置2孔平面钢闸门,单孔单孔净宽4.5m:机排流量 21.4m/s,设置5台立式轴流泵(单机功率 280kW),该工程规模为中等,等别为III等,主要建筑物级别为3级.该工程总体布置(顺水流方向)依次为内江铺盖段、闸站主体段(包括变电及控制室等上部建筑物)、外江消力池段、外江海漫段.其中闸站主体,纵向长13.9m,闸站基础采用钻孔灌注桩(Φ1.2m,共50根)处理,桩底持力层为圆砾层;内江铺盖段,纵向长20.0m,铺盖为现浇钢筋混凝
收稿日期:2016-09-26
作者简介:单伟(1985-),男,浙江临安人,頭士,工程师,主
要从事水利水电工程规划与建设管理工作万方数据
土结构,左右翼墙(扶壁式结构)间距净宽36.0m,墙高10.5m,铺盖及翼墙底部采用松桩基础;外江消力池段,纵向长度35.1m,底板为钢筋混凝土结构,左右翼墙(扶壁式结构)间距净宽36.0m,墙高 6.0~10.5m,底板及翼墙底部采用松桩基础;消力池外20.0m范围内采用合金笼网兜护底,平均厚 1.5m,宽36m.金家桥排涝闸站施工,涉及到深基坑开挖,该位置临近富春江(距主流段仅100m),且处于砂砾地层,并受周围环境限制,因此,研究如何采取相应工程技术措施进行深基坑的施工成为工程的重要技术难题
水文地质条件与周边环境 1.1水文条件
根据勘察报告中对地下水的描述,该场地地下水类型为孔隙潜水及孔隙承压水,地下水埋深为 0.5 ~2.8 m.